Baku:The 20 September station of Baku Metro CJSC is slated for full commissioning by the first half of next year. Construction at the station has been completed, and finishing works are currently underway, as reported by Mammad Rzayev, Head of the Construction Projects Management Department of Baku Metro CJSC.
According to Azeri-Press news agency, Rzayev stated that several elements related to the special architectural design of the 20 September station have been addressed. Issues concerning the import of materials and logistics have been resolved, allowing work to continue according to schedule.
The primary focus is currently on completing the station’s finishing works, with the goal of full commissioning by mid-next year. Rzayev also discussed ongoing projects, including a tunnel between the 28 May and Nizami stations. Excavation on the 211-meter tunnel has begun, with 63 meters already completed, and work is progressing as planned.
Rzayev mentioned that the tunnel is intended to become the Nizami-Jafar Jabbarli tunnel in the future.