Kazakhstan reduced terms for issuance of construction documents

Closed
by February 7, 2017 Business

“The new rules regulate and optimize the implementation of the three main stages of design, construction and installation works. The first stage – the issuance of initial permits, the second stage – approval of the draft design and the third stage of the commissioning of facilities”, – the statement reads.

The first step is the issuance of architectural and planning design for up to 30 days. Period of initial issuance of permits for design and construction reduced more than twice – from 40 to 17 working days depending on the complexity of the project.

The second stage is the coordination of draft design for up to 20 days. The term coordination of draft design has been reduced from 60 to 15 working days depending on the complexity of the project.

Thus, the third stage – is the issuance of a building permit for up to 10 days. The procedure for issuance of building paper permitshas been replaced by a notification in electronic form.

Recall, on January 1, 2016 the practical phase of the implementation of the National Plan – “100 concrete steps to implement the 5 institutional reforms was started. The construction sector is also covered by these reforms.

Source: Kazakhstan 2050